Woodhaven Pedestrian Pathway Realignment and Bridge Repair
Client: Town of Okotoks
Consultant: ISL Engineering
Start Date: September 2014
Completion Date: December 2014
Project Scope:
Repair bridge after 2013 flood damage
Install new footing and re-erect existing bridge abutment
Placement of pedestrian bridge on newly constructed abutments
Supply and install abutment erosion protection
Utilize structural steel to raise elevation above 2013 flood levels
Re-align and repair damaged pathway
*Picture taken upon completion of construction
Relocate +/- 100 Linear Metres of Public Pathway
Start Date: May 21, 2015
Completion Date: May 28, 2015