Didsbury Landfill - Phase V Construction
Client: Mountain View Regional Waste Management Commission
Consultant: Tagish Engineering (Red Deer, AB)
Start Date: March 2014
Completion Date: April 2014
Project Scope:
Excavate +/- 60,000 m³ future class II landfill cell
Supply and install leachate collection system, including perforated leachate collection pipes, wash rock, geotextile wrap, and manholes
Installation of a 600 mm thick clay liner
Installed +/- 12,000 sq. ft. 80 mil SDPE liner, including cleaning and fusing to existing liner
Install tire shred drainage layer and filter geotextile