Camrose Regional Landfill Cell 21
Client: The City of Camrose
Consultant: WSP / MMM Group
Start Date: June 2017
Completion Date: September 2017
Project Scope:
Excavate, haul and stockpile ~10,000 m³ of topsoil & subsoil
Excavate, haul and stockpile ~15,000 m³ common material
Import and place ~15,000 m³ clay material from borrow
Install ~20,000 m³ compacted clay liner and clay liner end slopes including subgrade preparation
Supply and place perforated and non-perforated HDPE leachate collection pipe including geotextile and drainage rock
Supply and install leachate collection manholes and associated fittings
Load, haul and place ~26,000 m² of tire shred drainage layer
Load, haul and place ~26,000 m² of 1 meter thick garbage frost cover layer
Supply and install 300 mm to 500 mm CSP drainage culverts