Shell Shantz Sulfur Remelt Pit Development
Devcon was contracted to support the development of a sulfur remelt pit at the Shell Shantz site. The
scope included discovery excavation, removal of contaminated and unsuitable materials, removal and
reinstallation of concrete lock blocks, construction of a hopper loading ramp, and final site restoration.
The project required careful coordination and precision work on an active industrial site, with a strong focus on safety, environmental compliance, and efficiency. All work was completed within a compressed schedule while maintaining quality standards and long term site functionality.
50
K
Contract Value
3
Pieces of Heavy Equipment Used
1
Month to Complete
300
T
Material Moved